PMO vs project office vs programme office: what's the difference?

By Stuart Lester, reviewed by Martin Brodie-Lynch

Last updated

The short answer

"PMO" is the umbrella term, and the other names describe what the office supports. A project office supports one project. A programme office supports a group of related projects working towards the same outcome. A portfolio office looks across everything the business is delivering and helps decide what to fund. Most mid-sized businesses need one permanent PMO that does a little of each, not separate offices.

The four types of office

UK guidance on project offices, known as P3O, describes four types:

  • Project office. Supports a single project with planning, reporting, the RAID log and document control. It's usually temporary and closes when the project ends.
  • Programme office. Supports a programme: several related projects delivering a shared change. It coordinates dependencies between projects and tracks whether the expected benefits are being delivered. It lasts for the life of the programme.
  • Portfolio office. Looks across every project and programme in the business. It gives the board the information to decide what to start, continue, pause or stop, and where to put people and money. It's permanent, and there's usually only one.
  • Centre of excellence. Focuses on capability rather than delivery. It owns the standards, methods, templates and training that every project and programme uses. In smaller businesses, this role usually sits inside the main PMO.

How they compare

  • Project office

    Supports
    One project
    How long it lasts
    Life of the project
    Main question it answers
    Is this project on track?
  • Programme office

    Supports
    A group of related projects
    How long it lasts
    Life of the programme
    Main question it answers
    Are we delivering the change and its benefits?
  • Portfolio office

    Supports
    Everything the business delivers
    How long it lasts
    Permanent
    Main question it answers
    Are we doing the right projects?
  • Centre of excellence

    Supports
    How delivery is done
    How long it lasts
    Permanent
    Main question it answers
    Are we doing projects the right way?

The name matters less than the job

“I've seen teams spend months debating what to call their PMO. The name matters far less than agreeing whether it supports projects, controls them, or decides which ones get funded.”

Stuart Lester

That choice is about how much control the office has. PMOs are commonly described as supportive (templates and guidance), controlling (standards that projects must follow) or directive (managing projects directly). Our guide to what a PMO does explains each type.

What a mid-sized business usually needs

A business running somewhere between 5 and 30 projects rarely needs separate project, programme and portfolio offices. One permanent PMO typically:

  • sets the standards and templates (the centre of excellence role)
  • runs consistent reporting across all projects (the project office role)
  • gives the board one view to prioritise from (the portfolio office role)

A temporary programme office is worth adding only when a single large change, such as a system replacement or a merger, needs its own coordination for a year or more.

About the author

Stuart Lester, Founder and CEO, Quantum Consultancy Ltd

Stuart Lester

Founder and CEO

View profile

Reviewed by Martin Brodie-Lynch

FAQs

Is a PMO the same as a project office?

Not quite. "PMO" is the general term. A project office is one specific type that supports a single project, while a PMO can cover many projects or the whole portfolio.

What's an enterprise PMO?

An enterprise PMO (EPMO) is a permanent office working at the top of the business. It usually combines the portfolio office and centre of excellence roles, and connects projects directly to strategy.

Do we need a portfolio office?

You need its function, a clear basis for deciding what to fund and stop, once you have more projects than people and money to deliver them. In a mid-sized business, that function is usually part of the main PMO rather than a separate office.

What is P3O?

P3O stands for Portfolio, Programme and Project Offices. It's UK best-practice guidance on designing and running these offices, and it's where the four types above come from.

Not sure which kind of PMO you need?

Book a 30-minute call and we'll tell you honestly how much PMO your business needs.

Book a 30-minute call