What goes in a RAID log, and who owns it?

By Martin Brodie-Lynch, reviewed by Stuart Lester

Last updated

The short answer

A RAID log is one place to record a project's risks, assumptions, issues and dependencies. Each entry has a named owner, a clear next action and a date. The project manager owns the log as a whole, the PMO combines logs across projects, and the log is reviewed every week or fortnight. A RAID log is only useful if it's kept current.

What the four letters mean

  • Risks. Things that might happen and would affect the project if they did. Example: a key supplier may not deliver on time.
  • Assumptions. Things you're treating as true without having proved them. Example: the existing system can handle the extra volume.
  • Issues. Things that have already happened and need action now. Example: the test environment isn't available.
  • Dependencies. Things the project relies on from elsewhere, or that others rely on from the project. Example: go-live depends on another team's data migration.

Some organisations use the D for decisions instead of dependencies, or track both. What matters is that the team agrees which it is.

What to record for each entry

Keep the columns to the minimum people will actually keep up to date:

  • For every entry: a reference number, a short description, the owner, the next action, the due date and the status.
  • Risks: likelihood, impact, and the response (what you'll do to reduce it).
  • Assumptions: how and by when it will be checked, and what happens if it turns out to be wrong.
  • Issues: severity, and whether it needs escalating beyond the project.
  • Dependencies: who it depends on, and the date it's needed by.

Why RAID logs fail

“Most RAID logs I've inherited weren't wrong, they were stale. Risks were logged at kick-off and never reviewed, so when something went wrong it had been sitting there, unowned, for months.”

Martin Brodie-Lynch

The usual reasons:

  • Entries are owned by a team or "TBC" rather than a named person.
  • The log is reviewed only when something has already gone wrong.
  • Assumptions are never checked, so they quietly turn into issues.
  • Closed items are deleted, so nobody can see what was learned.
  • The plan and the log are kept in separate places, so they drift apart.

Who owns what

  • The project manager owns the log and makes sure it's reviewed.
  • Each entry has one named owner responsible for the next action.
  • Anyone on the project can raise a new entry.
  • The project board sees the top risks and issues and decides on anything outside the project manager's authority.
  • The PMO sets the template and combines logs to show risks and issues across all projects.

Keeping it current

  • Review it at a fixed point every week or fortnight, as a standing item in the project meeting.
  • Ask the same three questions of each open entry: is it still valid, has the owner acted, and has anything changed?
  • Turn assumptions into risks or issues as soon as they prove doubtful.
  • Close entries rather than deleting them, so there's a record.
  • Keep the log in the same place as the plan, so a slipped date and its cause are seen together.

About the author

Martin Brodie-Lynch, COO and Co-founder, Quantum Consultancy Ltd

Martin Brodie-Lynch

COO and Co-founder

View profile

Reviewed by Stuart Lester

FAQs

What's the difference between a RAID log and a risk register?

A risk register records only risks. A RAID log also records assumptions, issues and dependencies, giving a fuller picture of what could affect the project.

Does PRINCE2 use a RAID log?

Not by that name. PRINCE2 uses a risk register and an issue register, along with other logs. Many organisations combine them into a RAID log because it's simpler to manage in one place.

How often should a RAID log be reviewed?

Weekly for active projects, or fortnightly for slower ones. Anything urgent is escalated straight away, not saved for the review.

Should the RAID log go to the board?

Not the full log. The board should see the handful of top risks and issues that need their attention or decision.